Czech bypass project faces delay

An important Czech bypass project is facing delays.
Road Structures / September 18, 2020 20 seconds Read
By MJ Woof
An important bypass project in the Czech Republic is now facing delays - image © courtesy of Artof Sha, Dreamstime.com
Delays are now affecting construction work for the Czech Republic’s Ceske Budejovice bypass project. As a result, the bypass will not be ready for traffic until 2024.

Geological problems in the Pohurka Tunnel are at the heart of the delays. Dealing with unexpectedly high levels of groundwater will add around €3.88 million to the project. In all, the project is costing around 204.9 million.
catfish1