More tenders for the Lower Thames Crossing

The winners will build 23km of road connecting to what will be the UK’s longest road tunnel.
By David Arminas April 2, 2021 Read time: 4 mins
The proposed northern tunnel entrance approach, looking south (artist image courtesy Highways England)
The proposed northern tunnel entrance approach, looking south (artist image courtesy Highways England)

Highways England has opened tenders to build two linking roads as part of the €2.23 billion (£1.9 billion) Lower Thames Crossing tunnel project near London.

The tunnel bore will house two 4km tunnels - one for southbound traffic, one for northbound traffic - beneath the River Thames. The bore will be 16.4m in diameter – the third widest bored tunnel in the world.

For more than 65 years the Dartford Crossing has been the only River Thames crossing between counties Kent and Essex. Highways England – the government agency responsible for England’s major roads and motorways - says that the ageing bridge and tunnel combination is designed for 135,000 vehicles a day. But it now often sees 180,000 a day which creates congestion at peak periods.

The agency says the planned Lower Thames Crossing will improve journeys by almost doubling road capacity across the river. The motorway will have a free-flow charging system where drivers do not to stop but pay remotely, similar to that at the existing Dartford Crossing. There will also be traffic regulation measures that include prohibiting use by pedestrians, low-powered motorcycles, cyclists, horse riders and agricultural vehicles.

In 2016, Highways England has appointed CH2M, Arcadis and COWI to work as joint venture partners in delivering the technical assistance for the project. Construction work could start in early 2022.

The two successful bidders will build 23km of road in total that will connect the longest road tunnel in the UK to the country’s strategic road network.

Kent Roads contract

The €705 million (£600 million) Kent Roads two-stage design and build contract is a for the route from the A2/M2 corridor to 1km south of the southern tunnel entrance, including strategic utilities and environmental interfaces. Work includes 6km of road, including a multi-level junction to connect the A2 to the Lower Thames Crossing. Two so-called “Green Bridges” at Thong Lane & Brewers Road, will combine green spaces with walking, cycling and vehicle access and provide better connectivity for the landscape, ecology and habitats. Brewers Road will also cater for horse riders.

The proposed Thong Lane green bridge linking the towns of Gravesend and Thong and the approach to the southern tunnel entrance, looking north (artist image courtesy Highways England)
The proposed Thong Lane green bridge linking the towns of Gravesend and Thong and the approach to the southern tunnel entrance, looking north (artist image courtesy Highways England)

The €1.53 billion (£1.3 billion) Roads North of the Thames contract - also a two-stage design and build deal - will deliver the route from 1km north of the northern tunnel entrance to Junction 29 of the M25 motorway. New link roads are required to connect the route with the M25, A13 and A1089. The contract comprises 16km of road to take the route through the A13 and to join the M25 at Junction 29. Five green bridges are combine planned.

The successful bidders and their supply chains will help make the Lower Thames Crossing the most environmentally sustainable road project ever delivered in the UK, according to Highways England. The winners will support delivery of landscaping that will increase the biodiversity value of the area by 15% by planting over 260 hectares of woodland, converting 400 hectares of arable land into semi-natural habitats and creating new ponds, waterways, ditches and hedgerows. Seven green bridges will connect habitats and species either side of the new road.

The two roads contracts are the final of package of three main works packages to be procured for the scheme. Already awarded are the €2.35 billion (£2 billion) Tunnels and Approaches package and the €191 million (£162.5 million) Integration Partner contract awarded to Jacobs earlier in the year.

“Our challenge is to build the new crossing in a way that not only supports the next generation of low carbon vehicles, but minimises our footprint, and allows us to enhance the natural environment and leave a positive legacy for our neighbours and users,” said Matt Palmer, executive director of the Lower Thames Crossing project.

The existing Dartford Crossing, up-river from the planned new crossing, consists of two bored tunnels and the cable-stayed Queen Elizabeth II Bridge. It is the only fixed road crossing of the River Thames east of London and, as such, is the busiest estuarial crossing in the UK. It opened before the M25 existed and opened in stages: the west tunnel in 1963, the east tunnel in 1980 and the bridge in 1991.
 

END