A roundabouts way of lighting

One of Europe’s first smart lighting systems specifically for roudabouts is operating in Hungary and making big energy savings for local government, explains Miklós Muranyi*
By Miklós Muranyi October 10, 2022 Read time: 4 mins
The lamps poles - which are casting long black shadows - are located only on the roundabout island and at a bicycle crossing (image courtesy NIF)
The lamps poles - which are casting long black shadows - are located only on the roundabout island and at a bicycle crossing (image courtesy NIF)

The roundabout at the south end of Andornaktálya village was completed in the summer of 2018 as part of the construction of express road M25 in north-east Hungary. Experiences gained since it was commissioned showed that the intersection needed good lighting for the safety of drivers and cyclists alike.

A solar panel lighting system was installed which has a storage capacity sufficient to cover the energy needs of the functional lighting all year round. Power for the lighting is provided using solar panels to supply rechargeable batteries which provide power to the lights.

Solar panels sit atop each lamp pole (image courtesy NIF)
Solar panels sit atop each lamp pole (image courtesy NIF)

The core feature of this solution is that light is provided in the intersection using candelabra-style lights on top of the poles installed on the roundabout island and also at bicycle crossings (see aerial image). This means that those entering the intersection will not encounter any separate functional lighting columns. In other words, only those lights needed for the motorist/cyclist will be powered up from a low level to full strength as vehicles approach.

This custom-developed functional lighting works independently of the grid. The LED lamps provide a light level of 10 lux by default in the roundabout and 15 lux at the cycle crossing.

However, a fixed power connection has also been installed as backup in case the solar system does not generate sufficient power. This is useful during winter when night comes sooner and there are fewer hours of sunlight to recharge the batteries. In this case, when the batteries drain to 60%, the system automatically switches to the fixed power connection. The system continues to run off the grid until the solar system again generates sufficient energy to recharge the batteries – but not necessarily to full capacity – and they can then operate the system safely.

This functional lighting was installed last November. Once the pilot was over, the system was fine-tuned further from the beginning of the year, and is now working perfectly. Ever since the final adjustment, it has never been necessary for the system to run off the grid.

Industrial motion detector sensors are situated on the lampposts at all four road entrances and at the bicycle route entry point. The sensors adjust light levels. This means that a significant proportion of energy can be saved, as the standard 10 lux lighting is automatically tuned down to 3 lux when the roundabout is not being used. As such, the roundabout is never without light at night, but has low lighting when not being used by vehicles or bicycles.

The complete functional lighting system of the roundabout has been integrated with the HDMR Smart City system controlled by road maintenance agency Magyar Közút Nonprofit. Importantly, the Smart City control centre can monitor and change the parameters of how the luminaires operate – a bi-directional, or two-way, information flow.

The main function of the HDMR Smart City system is to gradually decrease the light levels of the luminaires when it detects that the roundabout has been free of traffic for two minutes. However, when a car arrives, this is detected by a motion sensor, and by the time the car makes it to the roundabout, the luminaires receive a wireless signal which triggers an increase in light levels so that when the driver arrives at the roundabout the light is up to the standard level.

Miklós Muranyi
Miklós Muranyi

Compared to traditional sodium lights, the LED luminaires represent an energy saving of 50%. In addition, thanks to the HDMR motion sensor technology, the system is capable of saving up to an additional 40% on average.  

*Miklós Muranyi is chief coordination engineer at NIF, Hungary’s National Infrastructure Development Corporation. He heads up the preparation and implementation of state-financed motorway and railway projects and manages partnerships with foreign organisations. Muranyi is a civil engineering graduate from the Technical University of Budapest.


Who’s who

The system cost around US$101 million (€100 million) and installation took four months. Similar systems are being trialled at several motorway rest areas.

Client:
NIF - Nemzeti Infrastruktúra Fejlesztő (National Infrastructure Development Corporation) – a government agency which reports to the Ministry of Construction and Investment.
https://nif.hu

General contractor:
Zöld Garden, a green-space infrastructure specialist based in Dunaharaszti, near the Hungarian capital Budapest and which was responsible for constructing lighting infrastructure such as poles and ancillary stations.
https://zoldkoronagarden.hu

System operator/controller:
Magyar Közút Nonprofit, a state-owned agency established in 2005. It inspects and repairs pavement, landscapes highway routes, maintains road drainage systems and coordinates snow removal for the national road network, including motorways
www.kozut.hu

Lighting system:
HOFEKA, a lighting specialist, based near Budapest, that develops, designs and manufactures programmable light fixtures, parking assistance systems, waste management, charging electric cars, e-bikes and other devices. The company is ISO 9001 certified.
https://hofeka.hu/en

Related Content

Keestrack Company Profile

Keestrack has a strong reputation for innovative and cost-effective track mobile crushing and screening equipment with a relentless search for the best performance at the lowest cost per produced ton.

Keestrack introduced its hybrid and electric plug-in solutions in mobile processing technology in 2012.  At Conexpo Keestrack are presenting an overview of their extensive product range, introducing sustainable full electric plug-in equipment backed up by a drop-off engine/gen-set.

Keestrack, with its Texas based US Headquarters, will be at Conexpo with their American, Canadian and Latin American dealers.

Performance in every detail

The fully electric plug-in R5e impact crusher will be introduced to the American market. The impactor can be powered via mains connection for a zero carbon footprint, or via a gen-set unit, in the event of no available connection to the grid.

Keestrack B7
Keestrack B7

The R5e has a drop-off engine/gen-set which can be placed either on the chassis of the machine or besides the machine, connected with a power cable.

Being placed in a less dusty and vibrant environment maintenance is safer and easier when the engine is situated at ground level.

When connecting several machines to a single drop-off engine /gen-set, it results in huge savings as there is only one engine/gen-set to run and maintain.

Also on show: the H4e cone crusher in closed circuit, the award winning R3 impactor, the heavy duty B7 jaw crusher, the most mature and productive scalper on the market, the K6 and the dust suppression cannon W7.  


Central Hall, C-31386

Keestrack America
15066 US HWY 380 W
Krum
TX 76249
USA
[email protected]
www.keestrack.com

CONEXPOCON/AGG 2023
Keestrack R5e
Share
boombox1
boombox2